TM 10-5410-228-24
This task covers:
a. Removal
c. Assembly
b. Disassembly
d. Installation
INITIAL SETUP
Tools/Test Equipment:
Equipment Conditions:
Shop Equipment, Automotive Maintenance and
Power shut off, power panel and rear control panel
tagged.
ECU covers and doors opened or removed as
ECU work platform installed (reference
TM 10-5410-228-10).
NBC filter and plenum removed (see
TM 10-5410-228-10)
Personnel Required: (2)
References:
Materials/Parts:
TM 10-5410-228-10
Materials:/Parts: (Cont.)
The hydraulic system is pressurized. To prevent injury to personnel, gloves and eye
protection must be worn when working on hydraulic system.
NOTE
Plug open ports on hydraulic manifold and open ends of tube assemblies to keep the
(1)
Disconnect four tube assemblies (1) from four connectors (2) on hydraulic manifold (3). Remove
and discard four O-rings (4) from four connectors (2).
(2)
Remove four connectors (2) from hydraulic manifold (3). Remove and discard four O-rings (5)
from four connectors (2).
(3)
Plug open ports on hydraulic manifold (3) and open ends of four tube assemblies (1).
(4)
Disconnect five tube assemblies (6) from five elbows (7) on hydraulic manifold (3). Remove and
discard five O-rings (8) from five elbows (7).
(5)
Remove five elbows (7) from hydraulic manifold (3). Remove and discard five O-rings (9) from
five elbows (7).
(6)
Plug open ports on hydraulic manifold (3) and open end of five tube assemblies (6).
(7)
Disconnect two tube assemblies (10) from two connectors (11) on hydraulic manifold (3). Remove
and discard two O-rings (12) from two connectors (11).