TM 10-5410-228-24
This task covers:
a. Removal
b. Installation
INITIAL SETUP
Equipment Conditions:
Tools/Test Equipment:
Shop Equipment, Automotive Maintenance and
Power shut off. Power panel and rear control panel
tagged.
ECV parking brake set.
a. Removal
(1)
Remove screw (1) and clamp (2) securing thermistor A1RT1 (3) to recirculation fan (4).
(2)
Disconnect thermistor connector (5) from cable assembly 1A4A1W1 connector P1.
b. Installation
(1)
Connect thermistor connector (5) to cable assembly 1A4A1W1 connector P1.
(2)
Secure thermistor (3) to recirculation fan (4) with screw (1) and clamp (2).
P1
5
4
3
2
1
199-1-M
Figure 2-61. Thermistor Replacement
Follow-on maintenance: Install LMS guard per para 2.13.15, remove tags, apply power and perform
operational test.