5-5. REPAIR PARTS AND SUPPORT. Requisitions will
be forwarded to and filled by DCSC. Routing identifier
code (S9C) under milstrip procedures (AR 725-50) for
non-NSN items see Appendix H, for NSN Items see
Appendix 1. Requisitions should cite manufacturers part
numbers in the absence of NSNs.
5-6. PERSONNEL AND TRAINING
a. All operational and support personnel will
require training on the safe handling of nuclear devices
(see Para 4-12).
b. MOS Training: TRADOC will manage and
coordinate the MOS training of operators. This training
will be conducted by the 51 Committee (51 G) at Ft.
Leonardwood, MO.
5-7.
EQUIPMENT PUBLICATIONS
a. Initially two sets of the Commercial Instruction
Manuals, supplemented by a separate SOMARPI and TB
385-1 03 (Safety Procedures) were issued to support the
soil tester.
b. After initial issue of Tester, the manufacturers
manuals, the SOMARPI and TB 385-103 were combined
into this manual.
5-8.
FACILITIES
a. No special maintenance facilities are required
for the tester.
b. For storage facilities, see Section IV, Para 4-
17 and 4-18.
5-9.
EQUIPMENT IMPROVEMENT
RECOMMENDATION (EIRS). EIRs will be submitted in
accordance with instructions contained in DA PAM 738-
750.
5-10. DESTRUCTION TO PREVENT ENEMY USE.
When the tester cannot be evacuated the following will
be done:
a. Remove the circuit boards and display panel
(loosen and remove the four screws located in the
corners of the testers display panel, pull off panel, and
cut or disconnect wiring).
b. Destroy the display panel and circuit boards
by crushing.
c. Destroy worksheet and logs by crushing,
tearing, and burying, or scattering over a sufficiently
large area to make recovery improbable.
d. Abandon the remainder of the tester.
5-11.
PROCEDURE. In addition to operating and
maintenance
instructions,
see
Section
IV,
Safety
Procedures, in this manual.
5-12.
MANUFACTURERS SAFETY DEFECTS. If any
manufacturers safety defects occur, upon notification
TACOM will advise users on action to be taken for
correction and reporting.
5-13.
MANUFACTURERS FIELD CAMPAIGNS AND
MODIFICATIONS. Modifications are not anticipated. If
necessary, they will be applied by CPN after TACOMs
approval of the field campaign or modification plan.
5-14.
BASIC ISSUE ITEM LIST. List of items which
accompany the tester or are required for installation,
operation. or operator maintenance (Appendix C).
5-15.
PERSONNEL DOSIMETRY. See Section IV in
this manual.
5-16.
SHIPPING
INSTRUCTIONS.
Shipping
Information for Tester, Density and Moisture, Nuclear
Method,
NSN
6635-01-030-6896.
For
additional
information see paragraph 4-20.
a. Consult with the unit Transportation Officer to
insure that the tester is shipped in accordance with
Department of Transportation Regulations (Title 49 CFR
Parts 170-189) AR 385-11, TM 38-250, and the Nuclear
Regulatory Commission Regulations (Title 10 CFR Part
71). For CONUS, a commercial shipper should be used
to transport the tester.
b. The following information is provided to assist
in the preparation of shipping papers for the tester (Title
49 CFR Parts 172-173):