TM 10-5410-228-10
CBPS Performance Measures (LMS Crew)
REFERENCES:
TM 10-5410-228-24............. Unit, Direct Support and General Support Maintenance Manuals
for Chemical Biological Protective Shelter (CBPS) System
TM 10-5410-228-24P .......... Unit, Direct Support and General Support Maintenance Repair
Parts and Special Tools List for Chemical Biological Protective
Shelter(CBPS) System
GO
NO GO
1. Establish system in NBC mode.
____
____
2. Prepare Control Panel for System establishment.
____
____
3. Ensure EPG is disengaged prior to adjustment to ESS mode switch.
____
____
4. Assist air beam inflation.
____
____
5. Establish Talp Door.
____
____
6. Establish AMB Door.
____
____
7. Establish internal ABS.
____
____
8. Provide AC power to ABS.
____
____
9. Prepare ABS to receive patients.
____
____
10. Switch from Internal (INT) to External (EXT) power.
____
____
11. Complex systems.
____
____
12. Strike systems.
____
____
Change 1
G-3/(G-4 blank)