TM 10-5410-228-10
2.24.2.5
Direct Complexing Shelter (DCS).
The following steps describe procedures for connecting two or more CBPSs together in a side-by-side, DCS
configuration.
a. Cab Crew Tasks
(1)
Position ECVs and ground cloths (1, figure 2-22) facing opposite directions, side by side so that
space between inflated ABSs is one to three feet. Overlap ground cloths (1) between lines (2) on
ground cloth extensions (3) by about six inches.
(2)
Deploy each system per para 2.24.2.1 through para 2.24.2.4.
Figure 2-22. Positioning Ground Cloths for DCS
2-91